Change Order No. 1

Proposal

Change Order No. 1

Contract Date

November 23, 2026

Prepared By

Your Company

Presented To

Your Client

123 Street Name, Ste 987

Sampletown, XY 50001

This Change Order is made on November 23, 2026 between Your Company ("Contractor") and Your Client ("Owner"). It changes the Construction Contract between them dated [date of the contract, for example: April 6, 2026], with an original contract price of $62,500 (the "Contract").

 

1. The Change

Contractor will add LED under-cabinet lighting along all upper cabinets, on a dimmer switch, and two additional GFCI countertop outlets on the island side of the kitchen.

 

2. Reason

Requested by Owner during the electrical rough-in, so the new wiring can be run before the walls are closed.

3. Cost

The cost of this change, including overhead and profit.

Change Order No. 1

Description Units Unit Price Total Price
Under-cabinet lighting and outlets

Materials, including LED strips, drivers, dimmer, outlets, and wire

1 $640.00 $640.00

Electrician labor (hours)

8 $95.00 $760.00

Drywall patch and paint touch-up

1 $220.00 $220.00

Overhead and profit (10%)

1 $162.00 $162.00
Total USD $1,782.00

4. Schedule

This change adds 2 working days to the schedule in the Contract.

 

5. Contract Price

  • Original contract price: $62,500
  • Previous change orders: $0
  • This change order: $1,782
  • New contract price: $64,282

 

This change is invoiced as its own payment when its work is done, and each invoice is due by the date on it.

 

6. Everything Else Stays the Same

All other terms of the Contract remain in effect and apply to this change. Once signed by both parties, this change order becomes part of the Contract. Contractor will begin the changed work when it receives Owner's signature.

 

By signing below, both parties agree to this change, its price, and its effect on the schedule.

Signatures

You
Your Company
You